Data center fact sheet

Virginia

As of . Latest dated change shown: Sep 16, 2026. Source: Data Center Census (datacentercensus.com), CC BY 4.0.

Full state page

Tracked projects
14
2 proposed, 5 approved, 3 under construction, 1 paused, 1 cancelled, 2 denied
Planned capacity
2.9 GW
5 projects publish a figure; 6 projects publish none; 3 cancelled or denied not counted
Moratorium actions
1
Upcoming hearings
0

Projects

ProjectStatusPlanned capacityDeveloper
Stafford Technology Campus
Stafford County
Under construction1 GWStack Infrastructure
Crossroads Technology Campus
Spotsylvania County
Proposed894 MWRCK Digital Crossroads LLC
Amazon Web Services Louisa County campuses
Louisa, Louisa County
Under construction600 MWAmazon Web Services
Google Botetourt County Data Center Campus
Botetourt County
Approved300 MWGoogle
QTS Richmond campus expansion (RIC4 and RIC5)
Sandston, Henrico County
Approved110 MWQTS
Amazon Data Services King George campus (former Birchwood power plant site)
King George County
Pausednone publishedAmazon Data Services
Amazon Web Services Warrenton Data Center
Warrenton, Fauquier County
Approvednone publishedAmazon Web Services
Balico data center campus and gas plant
Chatham, Pittsylvania County
Deniednone publishedBalico LLC
Devlin Technology Park
Bristow, Prince William County
Approvednone publishedStanley Martin Homes
Google Chesterfield County data center campuses
Chesterfield County
Under constructionnone publishedGoogle

Largest 10 of 14 shown. All projects.

Pauses and local rules

JurisdictionActionWhenLength
Loudoun County[1]Vote to draft a pauseSep 2026—
  • Loudoun County: CPAM-2024-0001 and ZOAM-2024-0001 (Data Center Standards & Locations, Phase 1) (adopted, Mar 18, 2025)
  • Loudoun County: Loudoun County Zoning Ordinance maximum sound levels and data center noise study requirements (in effect)
  • Fairfax County: Data center zoning ordinance amendment (adopted, Sep 10, 2024)
  • Prince William County: Prince William County noise ordinance amendment (data centers and industrial uses) (adopted, Oct 28, 2025)

7 more on the local rules tracker.

Upcoming votes and hearings

No upcoming hearing on record. Agendas change; check with the body before attending.

Latest changes

Notes

Planned capacity adds each record’s first published figure for projects not cancelled or denied; projects that publish none are never estimated. IT load is the power reaching computing equipment, so a total that includes it understates total power. Locations may be approximate where a record gives only a town or county. Counts cover tracked projects, not every data center.

Sources

  1. DatacenterDynamics, “Virginia's Loudoun County board votes to pause new data center applications”, Sep 18, 2026. https://www.datacenterdynamics.com/en/news/virginias-loudoun-county-board-votes-to-pause-new-data-center-applications/
  2. Fredericksburg Free Press, “Spotsylvania Planning Commission recommends approval of 555-acre data center campus”, Sep 17, 2026. https://www.fredericksburgfreepress.com/2026/09/17/spotsylvania-planning-commission-recommends-approval-of-555-acre-data-center-campus/
  3. WJLA, “Loudoun County votes to pause new data center applications”, Sep 16, 2026. https://wjla.com/news/local/loudoun-county-data-centers-development-applications-board-supervisors-pause-northern-virginia-regulations-leesburg-catoctin-grid-reliability-dominion-energy-merger-power-lines-laws
  4. Cardinal News, “New details emerge about Botetourt grid upgrades for Google data center”, Sep 16, 2026. https://cardinalnews.org/2026/09/16/new-details-emerge-about-botetourt-grid-upgrades-for-google-data-center/
  5. Virginia Mercury, “Amazon changes course on water use for King George data center campus”, Aug 26, 2026. https://virginiamercury.com/2026/08/26/amazon-changes-course-on-water-use-for-king-george-data-center-campus/
  6. Spotsylvania County, “REC High Energy Use Facility (HEUF) Utility Information Form – Crossroads Technology Campus”, Aug 7, 2026. https://www.spotsylvania.va.us/DocumentCenter/View/41645/REC-High-Energy-Use-Facility-HEUF-Utility-Information-Form_Crossroads-Technology-Campus
  7. Tammy Purcell (Substack), “With eye toward rural preservation, planning commission gets details on proposed PDR program; DEQ issues controversial discharge permit for AWS data center campus by Lake Anna”, Jul 20, 2026. https://tammypurcell.substack.com/p/with-eye-toward-rural-preservation

Each project record lists all of its sources and excerpts. Cite as: Data Center Census, “Data center fact sheet: Virginia,” October 14, 2026, https://datacentercensus.com/fact-sheets/virginia.