Michigan
Data centers in Ingham County, Michigan
The Census tracks 1 data center project in Ingham County, Michigan, with 24 MW of published capacity: 1 cancelled. 1 moratorium action recorded.
Follow this county
New dated changes arrive in your feed reader or calendar. No account, no email address, no tracking.
- RSS feed for any feed reader
- Atom feed
- Hearings calendar (.ics, subscribes in Apple, Google or Outlook Calendar)
How many data centers are in Ingham County?
The Census tracks 1 major project here as of Nov 7, 2026: 1 cancelled. They are in Lansing. The largest by published capacity is Deep Green Lansing data center (24 MW).
Projects
| Project | Status | Capacity | Developer |
|---|---|---|---|
| Deep Green Lansing data center Lansing, Ingham County, MI | Cancelled | 24 MW | Deep Green |
Water and power
1 of the 1 tracked projects here has a disclosed water figure (1 in all), with sources and what each figure measures.
Moratoriums
| Jurisdiction | Action | Length | What the source says |
|---|---|---|---|
| Charter Township of Meridian Michigan · township |
Adopted May 19, 2026 |
6 months | Ordinance 2026-03 pauses data center applications while the township develops regulations. Charter Township of Meridian, MISource excerpt“establish a six month moratorium on data center applications” |
Recent changes
| Date | What changed | Project |
|---|---|---|
| Apr 6, 2026 | Deep Green withdraws its conditional rezoning request Lansing State Journal (via AOL) | Deep Green Lansing data center |
| Mar 2026 | Lansing Planning Commission approves the proposal, sending it to City Council Lansing Regional Chamber of Commerce | Deep Green Lansing data center |
| Feb 9, 2026 | Residents raise concerns about the proposal at a Lansing City Council public hearing WILX | Deep Green Lansing data center |
Ingham County data centers: common questions
How many data centers are in Ingham County, Michigan?
The Census tracks 1 major data center project in Ingham County as of Nov 7, 2026: 1 cancelled. That covers major sourced projects, not every smaller colocation or enterprise facility.
What is the biggest data center project in Ingham County?
By published planned capacity, Deep Green Lansing data center in Lansing, at 24 MW. Its status is cancelled.
Is there a data center moratorium in Ingham County?
Charter Township of Meridian adopted a data center moratorium (May 19, 2026), 6 months. Details and sources are in the moratorium tracker.
This page collects the county-level record: every tracked project, moratorium and local rule we can source for Ingham County. See all Michigan projects or look up projects near your ZIP code.
Cite this page
Last updated Nov 7, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). Data centers in Ingham County, Michigan. Retrieved from https://datacentercensus.com/us/michigan/ingham-county |
|---|---|
| MLA | “Data centers in Ingham County, Michigan.” Data Center Census, Nov 7, 2026, https://datacentercensus.com/us/michigan/ingham-county. |
| Link | https://datacentercensus.com/us/michigan/ingham-county |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.