U.S. data centers in August 2025

In August 2025, the Data Center Census recorded 23 dated changes at 18 tracked projects across 13 states.

Final report for August 2025, published September 1, 2025. Last data change: . Page rebuilt .

← July 2025 September 2025 → All reports · Monthly RSS

Dated changes
23
Projects with a first milestone
4
Moratorium actions
1
Court cases filed
1

The month in one paragraph

In August 2025, the Data Center Census recorded 23 dated changes at 18 tracked projects across 13 states. 4 projects have their earliest dated milestone in the month. Events recorded include 5 approvals, 1 denial, 1 cancellation. 1 moratorium action was recorded, 1 of them adopted, extended or announced. 1 court case was filed. That is 3 more than the 20 changes recorded in July 2025.

Counts describe what was recorded in this tracker, from published filings, notices and reports. They are not a measure of everything that happened in the industry, and a month’s counts can rise later if sources dated in it are added.

Compared with July 2025

MeasureAugust 2025July 2025Change
Dated changes recorded2320+3
Projects with a change1817+1
States13130
Projects with first milestone45−1
Approval events56−1
Denial events10+1
Cancellation events12−1
Construction or operations starts01−1
Moratorium actions110
Court cases filed10+1
Hearings and votes held000
Hearings and votes upcoming000

Projects with their first milestone in August 2025

ProjectFirst milestoneStatus now
AWS Wilmington data center
Wilmington, Clinton County, OH
Aug 7, 2025Approved
Compass Statesville
Statesville, Iredell County, NC
Aug 18, 2025Approved
Port Washington (Lighthouse) Data Center Campus
Port Washington, Ozaukee County, WI
Aug 19, 2025Under construction
Lake Hawkeye
Lansing, Tompkins County, NY
Aug 31, 2025Proposed

A project appears here when its earliest dated timeline entry is in this month. It does not mean it was announced publicly that month.

Every dated change

DateWhat changedProject
Aug 29, 2025CoreWeave signs additional 150 MW lease, bringing Polaris Forge 1 to 400 MW Applied DigitalPolaris Forge 1
Ellendale, Dickey County, ND · Operating
Aug 27, 2025Google announces Chesterfield data center as part of $9 billion Virginia investment Virginia BusinessGoogle Chesterfield County data center campuses
Chesterfield County, VA · Under construction
Aug 25, 2025Beale and TEP file special power agreement with Arizona Corporation Commission AZ LuminariaProject Blue
Tucson, Pima County, AZ · Under construction
Aug 22, 2025City Council unanimously adopts one-year citywide moratorium on data center applications Spectrum NewsProject Cumulus
St. Charles, St. Charles County, MO · Cancelled
Aug 21, 2025City reports planning commission approval of the 1,500-acre, 15-building plan City of Lebanon
Approval
Meta Lebanon Data Center
Lebanon, Boone County, IN · Under construction
Aug 20, 2025Metropolitan Development Commission approves rezoning 8-1 Mirror Indy
Approval
Google Franklin Township data center
Indianapolis, Marion County, IN · Cancelled
Aug 20, 2025LPSC approves Entergy Louisiana's three combined-cycle gas plants (~3,000 MW) and transmission for the data center Entergy
Approval
Meta Hyperion
Holly Ridge, Richland Parish, LA · Under construction
Aug 19, 2025Common Council approves Final Development Agreement with Vantage Data Centers City of Port Washington
Approval
Port Washington (Lighthouse) Data Center Campus
Port Washington, Ozaukee County, WI · Under construction
Aug 19, 2025Developer withdraws proposal ahead of City Council vote St. Louis Post-Dispatch (via GovTech)
Cancellation
Project Cumulus
St. Charles, St. Charles County, MO · Cancelled
Aug 19, 2025Vantage announces $25B Frontier campus Vantage Data CentersVantage Frontier Campus
Albany, Shackelford County, TX · Under construction
Aug 18, 2025Compass proposes a five-building campus on Stamey Farm Road DatacenterDynamicsCompass Statesville
Statesville, Iredell County, NC · Approved
Aug 18, 2025Fluidstack adds 160 MW CB-5 lease; Google backstop rises to about $3.2 billion TeraWulfLake Mariner
Somerset, Niagara County, NY · Operating
Aug 15, 2025WVDEP issues air quality construction permit R13-3713 after 1,605 written comments Parsons AdvocateRidgeline Facility
Thomas, Tucker County, WV · Approved
Aug 14, 2025TeraWulf signs 200+ MW, 10-year hosting agreements with Fluidstack; Google backstops $1.8 billion TeraWulfLake Mariner
Somerset, Niagara County, NY · Operating
Aug 7, 2025Wilmington City Council approves annexation of the project site Clinton County Port Authority (Choose Clinton County)
Approval
AWS Wilmington data center
Wilmington, Clinton County, OH · Approved
Aug 6, 2025Tucson City Council votes to end annexation negotiations, cutting off Tucson Water AZ LuminariaProject Blue
Tucson, Pima County, AZ · Under construction
Aug 1, 2025Land clearing begins, per Epoch AI Epoch AIVantage Frontier Campus
Albany, Shackelford County, TX · Under construction
Aug 2025A neighboring homeowner and business owner files a private nuisance lawsuit against Amazon over construction impacts Virginia MercuryAmazon Web Services Louisa County campuses
Louisa, Louisa County, VA · Under construction
Aug 2025Residents turn in 957 signatures to put the rezoning on the ballot (561 required) Bridge MichiganAugusta Township Data Center (Thor Equities)
Augusta Township, Washtenaw County, MI · Denied
Aug 2025Statesville Planning Board votes 6-0 to recommend the rezoning GovTech (The Charlotte Observer)Compass Statesville
Statesville, Iredell County, NC · Approved
Aug 2025City Council votes 5-2 in favor but short of required supermajority; request denied Community Impact
Denial
Highlander SM One data center
San Marcos, Hays County, TX · Denied
Aug 2025TeraWulf secures a long-term lease at the former Cayuga Power Plant site Ithaca TimesLake Hawkeye
Lansing, Tompkins County, NY · Proposed
Aug 2025Circuit Court Judge Kimberly Irving voids rezonings over improper public notice Virginia BusinessPrince William Digital Gateway
Gainesville, Prince William County, VA · Cancelled

Moratorium actions

JurisdictionActionDateSource
City of St. Charles
Missouri · one year
AdoptedAug 2025 Spectrum News

Full moratorium tracker →

Court cases filed

CaseProjectStatus
Newsom v. Amazon (private nuisance)
U.S. District Court for the Western District of Virginia (Charlottesville) · filed Aug 2025 Virginia Mercury
Amazon Web Services Louisa County campusespending

How this report is made

Generated from the Census records at build time. It lists dated timeline events, hearings, lawsuit filing dates and moratorium actions that fall in the month; each links to its project record and source. A month-only date belongs to its month. Entries dated only to a year are not placed in a month. Approval, denial, cancellation and construction counts are made by reading the wording of each dated event, so one event can count in more than one group, and a vote on a related item can be miscounted; open the linked record to read the source. Nothing is estimated.

The same data is behind the statistics page, the charts and the downloads.

Cite this page

Last updated Oct 14, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). U.S. data centers in August 2025. Retrieved from https://datacentercensus.com/reports/2025-08
MLA“U.S. data centers in August 2025.” Data Center Census, Oct 14, 2026, https://datacentercensus.com/reports/2025-08.
Linkhttps://datacentercensus.com/reports/2025-08

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.