- Tracked projects
- 2
- 1 under construction, 1 denied
- Planned capacity
- None published
- 0 projects publish a figure; 1 project publishes none; 1 cancelled or denied not counted
- Moratorium actions
- 0
- Upcoming hearings
- 0
Projects
| Project | Status | Planned capacity | Developer |
|---|---|---|---|
| Google Chesterfield County data center campuses | Under construction | none published | |
| Old Bermuda Data Center | Denied | none published | Washington Single Family Fund |
Pauses and local rules
No moratorium action on record.
Upcoming votes and hearings
No upcoming hearing on record. Agendas change; check with the body before attending.
Latest changes
- Jul 28, 2026 Project Skye's Virginia Water Protection permit application is on hold (Google Chesterfield County data center campuses)[1]
- Jun 3, 2026 Board of Zoning Appeals upholds the planning director's denial (Old Bermuda Data Center)[2]
- Jan 1, 2026 Chesterfield's new data center zoning rules take effect, requiring projects like this one to go before the Board of Supervisors first; the project's site plan had not been approved (Old Bermuda Data Center)[2]
- Aug 27, 2025 Google announces Chesterfield data center as part of $9 billion Virginia investment (Google Chesterfield County data center campuses)[3]
- May 28, 2025 Chesterfield supervisors approve zoning changes for two of the projects (Google Chesterfield County data center campuses)[1]
Notes
Planned capacity adds each record’s first published figure for projects not cancelled or denied; projects that publish none are never estimated. IT load is the power reaching computing equipment, so a total that includes it understates total power. Locations may be approximate where a record gives only a town or county. Counts cover tracked projects, not every data center.
Sources
- VPM News, “Chesterfield residents call for more transparency on Google data centers”, Jul 29, 2026. https://www.vpm.org/news/2026-07-29/google-alphabet-loch-skye-peanut-cfield-nda-deq-permits-zoning
- WWBT 12 On Your Side, “Chesterfield board upholds denial of Bermuda District data center”, Jun 3, 2026. https://www.12onyourside.com/2026/06/03/chesterfield-board-upholds-denial-bermuda-district-data-center/
- Virginia Business, “Google announces Chesterfield data center as part of $9B investment”, Aug 27, 2025. https://virginiabusiness.com/google-announces-chesterfield-data-center-as-part-of-9b-investment/
Each project record lists all of its sources and excerpts. Cite as: Data Center Census, “Data center fact sheet: Chesterfield County, Virginia,” October 14, 2026, https://datacentercensus.com/fact-sheets/virginia/chesterfield-county.