Company
Tract data centers
Tract, based in Denver, lines up land, power, fiber and zoning for data center campuses that other companies build. Its sister company, Fleet Data Centers, also owned by Tract Capital Management, develops and runs campuses of its own. The Census tracks 2 projects tied to Tract or Fleet, with their filings and news; the sourced company profile follows.
- Proposed 1
- Approved 1
Ranked #34 of 59 developers by the published capacity of its tracked projects that are proposed, approved, under construction or operating, as developer or operator (1.07 GW). See the ranking →
| Project | Status | Capacity | Developer | Last update |
|---|---|---|---|---|
| Farmington Technology Park Farmington, Dakota County, MN |
Approved | 708 MW | Tract | Sep 16, 2026 |
| Fleet Data Centers TRIC campuses (South Valley and Peru Ridge) Storey County, NV |
Proposed | 362 MW | Tract, Fleet Data Centers | Sep 18, 2026 |
Latest Tract data center news
The newest dated changes at Tract’s tracked projects, each from the filing, notice or report linked beside it.
-
Fleet Data Centers TRIC campuses (South Valley and Peru Ridge) NV
Public Utilities Commission of Nevada approves the two gas plants, subject to environmental permits and Storey County approvals Nevada Current -
Farmington Technology Park MN
City reports plaintiffs in both lawsuits involving the city have filed dismissals, pending final court direction City of Farmington -
Farmington Technology Park MN
Coalition announces it is withdrawing its lawsuit, citing litigation costs Blandin on Broadband (citing Sun This Week) -
Fleet Data Centers TRIC campuses (South Valley and Peru Ridge) NV
California Public Utilities Commission unanimously authorizes Liberty Utilities to seek bids for a new Lake Tahoe power supplier CapRadio -
Fleet Data Centers TRIC campuses (South Valley and Peru Ridge) NV
Fleet and Tract break ground on a 2 million sq ft data center along USA Parkway with Gov. Joe Lombardo in attendance KOLO 8 News Now -
Fleet Data Centers TRIC campuses (South Valley and Peru Ridge) NV
NV Energy states data centers did not influence the Liberty decision and it will serve Liberty until Greenlink West is in place KTVN 2News -
Fleet Data Centers TRIC campuses (South Valley and Peru Ridge) NV
Fortune publishes report linking NV Energy's Tahoe supply exit to data center demand Fortune -
Fleet Data Centers TRIC campuses (South Valley and Peru Ridge) NV
NV Energy enters large load electric service agreement with Fleet subsidiary SV RNO Property Owner 1, LLC This Is Reno / Nevada Current
Company profile
| What it does | Tract says it prepares shovel-ready data center sites, lining up power, fiber, zoning and entitlements in advance so developers can build faster (company description). [1] |
|---|---|
| Founded | Tract surfaced in August 2022, when DCD, citing The Australian Financial Review, reported that Columbia Capital, Cologix’s management team and the van Rooyen Family Office had formed a new data center firm. [2] |
| Headquarters | Tract is headquartered in Denver, Colorado. [3] |
| Leadership | Graham Williams is President of Tract; Grant van Rooyen, founder and CEO of Tract Capital Management, is its executive chairman. [4] |
| Ownership | Tract and Fleet Data Centers are both portfolio companies of Tract Capital Management (TCM), whose founder Grant van Rooyen chairs both. [4] Tract Capital describes Tract as its powered-land strategy for master-planned data center campuses and Fleet Data Centers as its mega-campus development strategy. [5] |
| Funding | A wholly owned subsidiary of Fleet Data Centers, Tract’s sister company, closed $4.6 billion of 6.500% senior secured notes due 2031 in May 2026 to fund a hyperscale facility in Storey County, Nevada. [5] |
| Stated footprint | Tract said in April 2026 that it had more than 25 GW of planned capacity and over 25,000 acres under control, naming campuses in eight states: Arizona, Illinois, Iowa, Minnesota, Nevada, Texas, Utah and Virginia (company claim; planned, not built, capacity). [6] |
| Notable | Farmington, Minnesota’s city council approved Tract’s rezoning, preliminary plat and comprehensive plan amendment for Farmington Technology Park on November 4, 2024. [7] Nevada’s utility commission approved a request by Tract Capital Management and Fleet Data Centers to build two gas power plants for data center projects at and near the Tahoe Reno Industrial Center, Nevada Current reported on September 18, 2026. [8] |
| Website | Tract’s website is tract.com. [1] |
- Home | Tract | Data Center Planning Tract, 2026-09-27
- ColCap and van Rooyen to launch new $1 billion data center fund known as Tract - DCD DatacenterDynamics (DCD), citing The Australian Financial Review, 2022-08-26
- Tract Enters Greater Chicago Market with the Acquisition of 343 Acres to be Developed as a 1GW Data Center Campus Known as the Morris Technology Park - Tract Tract, 2026-01-15
- Who We Are | Tract | Data Center Tract, 2026-09-27
- Fleet Data Centers Announces Closing of Upsized $4.6 Billion 6.500% Senior Secured Notes Offering to Fund Hyperscale Facility in Rapidly Growing Reno Hub - Tract Capital Tract Capital, 2026-05-01
- FERC Approves Transmission Security Agreement (TSA) Between ComEd and Tract, Advancing 1GW of Responsible Data Center Growth in Greater Chicago - Tract Tract, 2026-04-15
- Data Center (Farmington Technology Park) | Farmington, MN City of Farmington, Minnesota, 2026-09-16
- Public Utility Commission approves gas plants to power data centers • Nevada Current Nevada Current, 2026-09-18
Company self-descriptions and stated figures are the company’s own claims, dated where the source gives a date.
Tract’s planned capacity and acreage are the company’s own figures and describe land under its control, not built data centers. Fleet Data Centers projects are listed here because both companies belong to Tract Capital Management.