Company
Panattoni Development data centers: tracked projects and locations
Panattoni Development is linked to 4 tracked projects in Ohio, Kentucky, Michigan, Wisconsin, totaling 1.24 GW of planned capacity. Role: developer.
- Proposed 2
- Approved 1
- Under construction 1
Ranked #30 of 59 developers by the published capacity of its tracked projects that are proposed, approved, under construction or operating, as developer or operator (1.24 GW). See the ranking →
| Project | Status | Capacity | Developer | Last update |
|---|---|---|---|---|
| Perry Township Data Center Canton, Stark County, OH |
Under construction | 240 MW | Panattoni Development | Sep 1, 2026 |
| Project Bluegrass Burgin, Mercer County, KY |
Proposed | — | Panattoni Development | Sep 8, 2026 |
| Project Cannoli Van Buren Township, Wayne County, MI |
Approved | 1 GW | Panattoni Development | Oct 30, 2026 |
| Project Cornmaze Beloit, Rock County, WI |
Proposed | — | Panattoni Development | Aug 17, 2026 |
Latest Panattoni Development data center news
The newest dated changes at Panattoni Development’s tracked projects, each from the filing, notice or report linked beside it.
-
Project Cannoli MI
Michigan Attorney General petitions the Commission for rehearing of the contract approval, arguing the 20-year cost accounting could leave other customers subsidizing the data center in some years Michigan Public -
Project Cannoli MI
Van Buren Township Planning Commission votes 5-1 to approve the final site plan; the report says Google is the final owner and operator and Panattoni is managing construction Michigan Public -
Project Cannoli MI
Michigan Public Service Commission unanimously gives conditional approval to DTE Electric's 20-year special contracts to serve the Google campus, with protections including a minimum monthly billing demand and a termination payment Michigan Public -
Project Bluegrass KY
On the mayor's tie-breaking vote, Burgin City Council approves on first reading an ordinance for the city to rejoin the joint Mercer County, Harrodsburg and Burgin Planning and Zoning Commission WKYT -
Project Bluegrass KY
A planned council vote on directing the city attorney to draft an ordinance annexing the data center site does not happen after council member Melinda Wofford walks out and the council loses its quorum Kentucky Lantern -
Project Bluegrass KY
Mercer County Fiscal Court gives a first reading of the commission's data center regulations Kentucky Lantern -
Perry Township Data Center OH
Residents sue the Perry Township trustees, Panattoni and other local bodies over the noise ordinance and tax-exemption resolution; the suit does not seek to halt development Ideastream Public Media -
Project Cornmaze WI
Town of Beloit board votes 4-0 on a resolution calling for a 12-month data center moratorium; a public hearing and an ordinance are still required Beloit Daily News