Georgia
Data centers in Columbia County, Georgia
The Census tracks 2 data center projects in Columbia County, Georgia: 2 approved.
How many data centers are in Columbia County?
The Census tracks 2 major projects here as of Sep 22, 2026: 2 approved. They are in Harlem, Appling.
Projects
| Project | Status | Capacity | Developer |
|---|---|---|---|
| Pumpkin Technology Campus Harlem, Columbia County, GA | Approved | — | Cloverleaf Infrastructure (Piedmont DevCo LLC), with the Prather Company |
| White Oak Technology Park Appling, Columbia County, GA | Approved | — | Trammell Crow Company |
Recent changes
| Date | What changed | Project |
|---|---|---|
| Aug 2026 | Economic Development Authority of Columbia County approves a memorandum of understanding for a $17 billion data center investment by Kinetic Infrastructure Solutions, an Alphabet subsidiary; county says Google will pay $40 million a year for seven years WRDW | White Oak Technology Park |
| Jul 23, 2026 | Columbia County Economic Development Authority announces Google as sole end user and operator of the data center project DatacenterDynamics | White Oak Technology Park |
| Apr 13, 2026 | Guido files notices of appeal of the dismissals WRDW | Pumpkin Technology Campus |
| Apr 13, 2026 | Guido files notices of appeal to Georgia Court of Appeals WRDW | White Oak Technology Park |
| Mar 25, 2026 | Superior Court order dismissing the Pumpkin Center petition with prejudice is signed and filed WRDW | Pumpkin Technology Campus |
| Mar 25, 2026 | Columbia County Superior Court dismissal orders filed (White Oak order signed March 19) WRDW | White Oak Technology Park |
| Feb 25, 2026 | Resident Gregory P. Guido Jr. files a judicial review petition challenging the Pumpkin Center rezoning WRDW | Pumpkin Technology Campus |
| Feb 25, 2026 | Gregory P. Guido Jr. files judicial review petitions challenging White Oak and Pumpkin Center rezonings WRDW | White Oak Technology Park |
| Feb 2026 | Board of Commissioners approves the rezoning 4-1 with larger buffers and berms WRDW | Pumpkin Technology Campus |
| Feb 2026 | Board of Commissioners unanimously approves D-C data center rezoning with 65 dB noise cap; also approves Pumpkin Center, rejects Byrd Farms The Augusta Press | White Oak Technology Park |
| Jan 2026 | Columbia County Planning Commission votes 4-1 to recommend the Pumpkin Center and Byrd Farm data center projects WRDW | Pumpkin Technology Campus |
| Dec 2025 | Piedmont DevCo LLC applies to rezone about 420 acres for the Pumpkin Technology Campus The Augusta Press | Pumpkin Technology Campus |
Columbia County data centers: common questions
How many data centers are in Columbia County, Georgia?
The Census tracks 2 major data center projects in Columbia County as of Sep 22, 2026: 2 approved. That covers major sourced projects, not every smaller colocation or enterprise facility.
This page collects the county-level record: every tracked project, moratorium and local rule we can source for Columbia County. See all Georgia projects or look up projects near your ZIP code.
Cite this page
Last updated Sep 22, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). Data centers in Columbia County, Georgia. Retrieved from https://datacentercensus.com/us/georgia/columbia-county |
|---|---|
| MLA | “Data centers in Columbia County, Georgia.” Data Center Census, Sep 22, 2026, https://datacentercensus.com/us/georgia/columbia-county. |
| Link | https://datacentercensus.com/us/georgia/columbia-county |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.