U.S. data centers in May 2025

In May 2025, the Data Center Census recorded 14 dated changes at 14 tracked projects across 9 states.

Final report for May 2025, published June 1, 2025. Last data change: . Page rebuilt .

← April 2025 June 2025 → All reports · Monthly RSS

Dated changes
14
Projects with a first milestone
3
Moratorium actions
1
Court cases filed
1

The month in one paragraph

In May 2025, the Data Center Census recorded 14 dated changes at 14 tracked projects across 9 states. 3 projects have their earliest dated milestone in the month. Events recorded include 4 approvals, 1 denial. 1 moratorium action was recorded, 1 of them adopted, extended or announced. 1 court case was filed. That is 3 more than the 11 changes recorded in April 2025.

Counts describe what was recorded in this tracker, from published filings, notices and reports. They are not a measure of everything that happened in the industry, and a month’s counts can rise later if sources dated in it are added.

Compared with April 2025

MeasureMay 2025April 2025Change
Dated changes recorded1411+3
Projects with a change1410+4
States97+2
Projects with first milestone330
Approval events40+4
Denial events110
Cancellation events02−2
Construction or operations starts000
Moratorium actions10+1
Court cases filed110
Hearings and votes held000
Hearings and votes upcoming000

Projects with their first milestone in May 2025

ProjectFirst milestoneStatus now
Google Chesterfield County data center campuses
Chesterfield County, VA
May 28, 2025Under construction
Augusta Township Data Center (Thor Equities)
Augusta Township, Washtenaw County, MI
May 31, 2025Denied
Oakline at Mill Creek
Salem, OR
May 31, 2025Proposed

A project appears here when its earliest dated timeline entry is in this month. It does not mean it was announced publicly that month.

Every dated change

DateWhat changedProject
May 28, 2025Chesterfield supervisors approve zoning changes for two of the projects VPM News
Approval
Google Chesterfield County data center campuses
Chesterfield County, VA · Under construction
May 23, 2025Amazon says it is suspending its development activities in Minnesota but will keep the property MPR NewsAmazon Becker Data Center
Becker, Sherburne County, MN · Paused
May 14, 2025Metropolitan Council approves the Farmington Technology Park comprehensive plan amendment City of Farmington
Approval
Farmington Technology Park
Farmington, Dakota County, MN · Approved
May 2025County commissioners vote to sell county parcels for $26 million and rezone land to heavy industrial Inside Climate NewsAmazon Web Services Richmond County data center campus
Hamlet, Richmond County, NC · Under construction
May 2025Planning commission recommends denying the rezoning Planet Detroit
Denial
Augusta Township Data Center (Thor Equities)
Augusta Township, Washtenaw County, MI · Denied
May 2025Villa Rica approves annexation and rezoning for the data center (reported May 14, 2025) Times-Georgian
Approval
Avemore Data Park
Villa Rica, Carroll County, GA · Approved
May 2025Crusoe begins construction ABC 7 AmarilloGoodnight Campus
Claude, Armstrong County, TX · Under construction
May 2025County grants Woodland Caribou LLC 10-year tax breaks of up to 50% Indiana Daily StudentGoogle Morgan County Data Center
Monrovia, Morgan County, IN · Under construction
May 2025Fayetteville issues certificate of occupancy for the first building on the QTS campus Atlanta Journal-ConstitutionMicrosoft Fairwater Atlanta
Fayetteville, Fayette County, GA · Operating
May 2025The Oregon Department of Administrative Services signs a contract to sell 32.23 acres of land in the Mill Creek Corporate Center, with closing set for October 2026 KATUOakline at Mill Creek
Salem, OR · Proposed
May 2025Reports emerge of potential sale to Prologis DatacenterDynamicsProject Sail
Newnan, Coweta County, GA · Approved
May 2025First building occupied Atlanta Journal-ConstitutionQTS Fayetteville data center campus
Fayetteville, Fayette County, GA · Operating
May 2025Grayslake Village Board completes approvals of the campus (approved between September 2024 and May 2025) Lake and McHenry County Scanner
Approval
T5 @ Chicago IV
Grayslake, Lake County, IL · Approved
May 2025Initial rezoning vote The Augusta PressWhite Oak Technology Park
Appling, Columbia County, GA · Approved

Moratorium actions

JurisdictionActionDateSource
Coweta County
Georgia · 180 days
AdoptedMay 2025 The Atlanta Journal-Constitution

Full moratorium tracker →

Court cases filed

CaseProjectStatus
Amazon's vested-rights appeal against King George County
King George County Circuit Court · filed May 2025 GovTech (Richmond Times-Dispatch)
Amazon Data Services King George campus (former Birchwood power plant site)pending

How this report is made

Generated from the Census records at build time. It lists dated timeline events, hearings, lawsuit filing dates and moratorium actions that fall in the month; each links to its project record and source. A month-only date belongs to its month. Entries dated only to a year are not placed in a month. Approval, denial, cancellation and construction counts are made by reading the wording of each dated event, so one event can count in more than one group, and a vote on a related item can be miscounted; open the linked record to read the source. Nothing is estimated.

The same data is behind the statistics page, the charts and the downloads.

Cite this page

Last updated Oct 14, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). U.S. data centers in May 2025. Retrieved from https://datacentercensus.com/reports/2025-05
MLA“U.S. data centers in May 2025.” Data Center Census, Oct 14, 2026, https://datacentercensus.com/reports/2025-05.
Linkhttps://datacentercensus.com/reports/2025-05

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.