Data Center Census Near me

Monthly report

U.S. data centers in April 2025

In April 2025, the Data Center Census recorded 11 dated changes at 10 tracked projects across 7 states.

Final report for April 2025, published May 1, 2025. Last data change: . Page rebuilt .

← March 2025 May 2025 → All reports · Monthly RSS

Dated changes
11
Projects with a first milestone
3
Moratorium actions
0
Court cases filed
1

The month in one paragraph

In April 2025, the Data Center Census recorded 11 dated changes at 10 tracked projects across 7 states. 3 projects have their earliest dated milestone in the month. Events recorded include 1 denial, 2 cancellations. 1 court case was filed. That is 8 fewer than the 19 changes recorded in March 2025.

Counts describe what was recorded in this tracker, from published filings, notices and reports. They are not a measure of everything that happened in the industry, and a month’s counts can rise later if sources dated in it are added.

Compared with March 2025

MeasureApril 2025March 2025Change
Dated changes recorded1119−8
Projects with a change1019−9
States715−8
Projects with first milestone314−11
Approval events02−2
Denial events110
Cancellation events20+2
Construction or operations starts000
Moratorium actions01−1
Court cases filed110
Hearings and votes held000
Hearings and votes upcoming000

Projects with their first milestone in April 2025

ProjectFirst milestoneStatus now
Homer City Energy Campus
Homer City, Indiana County, PA
Apr 2, 2025Under construction
White Oak Technology Park
Appling, Columbia County, GA
Apr 9, 2025Approved
Little Rock Port data center
Little Rock, Pulaski County, AR
Apr 30, 2025Proposed

A project appears here when its earliest dated timeline entry is in this month. It does not mean it was announced publicly that month.

Every dated change

DateWhat changedProject
Apr 24, 2025Amazon files an 878-page petition with the King George County Circuit Court Fredericksburg Free PressAmazon Data Services King George campus (former Birchwood power plant site)
King George County, VA · Paused
Apr 15, 2025Board chairman denies withdrawal request; Board of Supervisors votes 6-1 to deny rezoning Cardinal News
Denial, Cancellation
Balico data center campus and gas plant
Chatham, Pittsylvania County, VA · Denied
Apr 14, 2025Balico announces it is withdrawing its application and exploring a residential subdivision instead WVTF / Radio IQ
Cancellation
Balico data center campus and gas plant
Chatham, Pittsylvania County, VA · Denied
Apr 11, 2025Taylor EDC sells the property to the developer for $10,000,000 City of Taylor, TXBlueprint Taylor Data Center
Taylor, Williamson County, TX · Approved
Apr 9, 2025DRI filed for 8M sq ft data center and technology park DatacenterDynamicsWhite Oak Technology Park
Appling, Columbia County, GA · Approved
Apr 9, 2025Aerial imaging shows 35 turbines operating, per SELC Southern Environmental Law CenterxAI Colossus
Memphis, Shelby County, TN · Operating
Apr 8, 2025Resident Greg Berns speaks against the proposed data center during citizen comment at a Spalding County Board of Commissioners meeting The Griffin Daily NewsProject Spalding
Spalding County, GA · Approved
Apr 2, 2025Homer City Redevelopment and Kiewit announce the natural gas-powered data center campus Homer City RedevelopmentHomer City Energy Campus
Homer City, Indiana County, PA · Under construction
Apr 2025Atlas Development files a Development of Regional Impact for the 428-acre technology and data park DatacenterDynamicsAvemore Data Park
Villa Rica, Carroll County, GA · Approved
Apr 2025Little Rock Board of Directors adopts a resolution authorizing a memorandum of understanding with Willowbend Capital LLC for a $1 billion, 300,000-square-foot data center by an unnamed company Arkansas BusinessLittle Rock Port data center
Little Rock, Pulaski County, AR · Proposed
Apr 2025Nearby residents file a lawsuit in Jefferson County Circuit Court challenging the rezoning WBRCProject Marvel
Bessemer, Jefferson County, AL · Approved

Court cases filed

CaseProjectStatus
Rock Mountain Lake Road residents v. City of Bessemer
Jefferson County Circuit Court · filed Apr 2025 WBRC
Project Marveldismissed

How this report is made

Generated from the Census records at build time. It lists dated timeline events, hearings, lawsuit filing dates and moratorium actions that fall in the month; each links to its project record and source. A month-only date belongs to its month. Entries dated only to a year are not placed in a month. Approval, denial, cancellation and construction counts are made by reading the wording of each dated event, so one event can count in more than one group, and a vote on a related item can be miscounted; open the linked record to read the source. Nothing is estimated.

The same data is behind the statistics page, the charts and the downloads.

Cite this page

Last updated Oct 14, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). U.S. data centers in April 2025. Retrieved from https://datacentercensus.com/reports/2025-04
MLA“U.S. data centers in April 2025.” Data Center Census, Oct 14, 2026, https://datacentercensus.com/reports/2025-04.
Linkhttps://datacentercensus.com/reports/2025-04

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.