- Tracked projects
- 1
- 1 approved
- Planned capacity
- 500 MW
- 1 project publishes a figure; 0 projects publish none
- Moratorium actions
- 0
- Upcoming hearings
- 0
Projects
| Project | Status | Planned capacity | Developer |
|---|---|---|---|
| Compass Statesville Statesville | Approved | 500 MW | Compass Datacenters |
Pauses and local rules
No moratorium action on record.
Upcoming votes and hearings
No upcoming hearing on record. Agendas change; check with the body before attending.
Latest changes
- Sep 14, 2026 Statesville City Council unanimously approves a 180-day moratorium on new data centers in the city; WBTV reports it will not affect previously approved data centers (Compass Statesville)[1]
- Sep 2025 Statesville City Council approves the rezoning 8-0 (Compass Statesville)[2]
- Aug 18, 2025 Compass proposes a five-building campus on Stamey Farm Road (Compass Statesville)[3]
- Aug 2025 Statesville Planning Board votes 6-0 to recommend the rezoning (Compass Statesville)[4]
Notes
Planned capacity adds each record’s first published figure for projects not cancelled or denied; projects that publish none are never estimated. IT load is the power reaching computing equipment, so a total that includes it understates total power. Locations may be approximate where a record gives only a town or county. Counts cover tracked projects, not every data center.
Sources
- WBTV, “Statesville unanimously approves 180-day moratorium on data centers: What we know”, Sep 15, 2026. https://www.wbtv.com/2026/09/15/statesville-unanimously-approves-180-day-moratorium-data-centers-what-we-know/
- GovTech (The Charlotte Observer), “Despite Protests, North Carolina City Approves Data Center”, Sep 16, 2025. https://www.govtech.com/products/despite-protests-north-carolina-city-approves-data-center
- DatacenterDynamics, “Compass Datacenters proposes 333-acre campus in Statesville, North Carolina”, Aug 18, 2025. https://www.datacenterdynamics.com/en/news/compass-datacenters-proposes-333-acre-campus-in-statesville-north-carolina/
- GovTech (The Charlotte Observer), “Government Board Backs Massive Data Center in Rural N.C.”, Aug 27, 2025. https://www.govtech.com/products/government-board-backs-massive-data-center-in-rural-n-c
Each project record lists all of its sources and excerpts. Cite as: Data Center Census, “Data center fact sheet: Iredell County, North Carolina,” October 14, 2026, https://datacentercensus.com/fact-sheets/north-carolina/iredell-county.