Data Center Census Near me

Data center fact sheet · county

West Feliciana Parish, Louisiana

As of . Latest dated change shown: Jun 15, 2026. Source: Data Center Census (datacentercensus.com), CC BY 4.0.

Full county page

Tracked projects
1
1 under construction
Planned capacity
330 MW
1 project publishes a figure; 0 projects publish none
Moratorium actions
0
Upcoming hearings
0

Projects

ProjectStatusPlanned capacityDeveloper
Hut 8 River Bend Campus
St. Francisville
Under construction330 MWHut 8

Pauses and local rules

No moratorium action on record.

Upcoming votes and hearings

No upcoming hearing on record. Agendas change; check with the body before attending.

Latest changes

  • Jun 15, 2026 West Feliciana Parish Council and Industrial Development Board accept an agreement for a $10 million PILOT prepayment from Hut 8 due July 1, 2026 (Hut 8 River Bend Campus)[1]
  • Dec 22, 2025 Parish president says parish permitting is complete; construction already under way (Hut 8 River Bend Campus)[2]
  • Dec 17, 2025 Hut 8 signs 15-year, 245 MW lease with Fluidstack; state and Entergy announce $10 billion project (Hut 8 River Bend Campus)[3]
  • Mar 18, 2025 Hut 8 announces it has secured 592 acres in West Feliciana Parish for River Bend (Hut 8 River Bend Campus)[4]

Notes

Planned capacity adds each record’s first published figure for projects not cancelled or denied; projects that publish none are never estimated. IT load is the power reaching computing equipment, so a total that includes it understates total power. Locations may be approximate where a record gives only a town or county. Counts cover tracked projects, not every data center.

Sources

  1. WBRZ, “West Feliciana Parish Council and Industrial Development Board accept agreement for prepayment from data center”, Jun 15, 2026. https://www.wbrz.com/news/west-feliciana-parish-council-and-industrial-development-board-accept-agreement-for-prepayment-from-data-center
  2. 10/12 Industry Report, “Hut 8 lands a massive partnership for its West Feliciana data center”, Dec 22, 2025. https://www.1012industryreport.com/technology/ai/hut-8-lands-a-massive-partnership-for-its-west-feliciana-data-center/
  3. Louisiana Economic Development, “Hut 8 Selects Southeast Louisiana as Site of $10 Billion Artificial Intelligence Data Center”, Dec 17, 2025. https://www.opportunitylouisiana.gov/news/hut-8-selects-southeast-louisiana-as-site-of-10-billion-artificial-intelligence-data-center
  4. DatacenterDynamics, “Hut 8 secures 592 acres for 300MW Bitcoin and AI data center”, Mar 18, 2025. https://www.datacenterdynamics.com/en/news/hut-8-secures-592-acres-for-300mw-bitcoin-and-ai-data-center/

Each project record lists all of its sources and excerpts. Cite as: Data Center Census, “Data center fact sheet: West Feliciana Parish, Louisiana,” October 14, 2026, https://datacentercensus.com/fact-sheets/louisiana/west-feliciana-parish.