Tracked projects
2
1 approved, 1 under construction
Planned capacity
512 MW
2 projects publish a figure; 0 projects publish none
Moratorium actions
0
Upcoming hearings
0

Projects

ProjectStatusPlanned capacityDeveloper
Project Borealis
Mesa
Approved300 MWNovva Data Centers
Compass Datacenters Goodyear Campus
Goodyear
Under construction212 MWCompass Datacenters

Pauses and local rules

No moratorium action on record.

Upcoming votes and hearings

No upcoming hearing on record. Agendas change; check with the body before attending.

Latest changes

  • Feb 3, 2025 City staff confirm the project, a permitted use in the Light Industrial district, does not have to go to the City Council (Project Borealis)[1]
  • Jan 2025 Mesa Planning and Zoning Board approves the project (Project Borealis)[1]
  • Aug 21, 2024 Novva announces a 300 MW campus in Mesa (Project Borealis)[2]
  • Aug 13, 2024 Mesa Design Review Board hears the plan under the name Project Borealis and takes no action, giving the applicant feedback (Project Borealis)[3]
  • Dec 8, 2023 Contractor Sundt marks completion of Building 3 on the campus (Compass Datacenters Goodyear Campus)[4]
  • Aug 2023 Novva wins a state land auction for about 165 acres in southeast Mesa with a $62.7 million bid (Project Borealis)[1]

Notes

Planned capacity adds each record’s first published figure for projects not cancelled or denied; projects that publish none are never estimated. IT load is the power reaching computing equipment, so a total that includes it understates total power. Locations may be approximate where a record gives only a town or county. Counts cover tracked projects, not every data center.

Sources

  1. ABC15 / Phoenix Business Journal, “$3 billion Mesa data center campus gets green light”, Feb 3, 2025. https://www.abc15.com/news/business/3-billion-mesa-data-center-campus-gets-green-light
  2. Novva Data Centers, “Novva Data Centers Announces New Campus in Mesa”, Aug 21, 2024. https://www.novva.com/media-center/novva-data-centers-announces-new-campus-in-mesa/
  3. ABC15 / Phoenix Business Journal, “Utah data center firm gears up for first Arizona project”, Aug 15, 2024. https://abc15.com/news/business/utah-data-center-firm-gears-up-for-first-arizona-project
  4. Sundt Construction, “Sundt Team Completes Building at Compass Datacenters’ Campus, Celebrating Major Milestone with Toy Drive for Local Nonprofits”, Dec 12, 2023. https://www.sundt.com/2023/sundt-team-completes-building-at-compass-datacenters-campus-celebrating-major-milestone-with-toy-drive-for-local-nonprofits/

Each project record lists all of its sources and excerpts. Cite as: Data Center Census, “Data center fact sheet: Maricopa County, Arizona,” October 14, 2026, https://datacentercensus.com/fact-sheets/arizona/maricopa-county.