Pike County, Ohio
As of . Latest dated change shown: Aug 17, 2026. Source: Data Center Census (datacentercensus.com), CC BY 4.0.
- Tracked projects
- 1
- 1 under construction
- Planned capacity
- 10 GW
- 1 project publishes a figure; 0 projects publish none
- Moratorium actions
- 0
- Upcoming hearings
- 0
Projects
| Project | Status | Planned capacity | Developer |
|---|---|---|---|
| PORTS-Pike Technology Campus Piketon | Under construction | 10 GW | SB Energy (SoftBank Group) |
Pauses and local rules
No moratorium action on record.
Upcoming votes and hearings
No upcoming hearing on record. Agendas change; check with the body before attending.
Latest changes
- Aug 17, 2026 OpenAI announces it has joined the project under a 20-year lease, with NVIDIA investing $1.5 billion (PORTS-Pike Technology Campus)[1]
- May 28, 2026 Permit filed with Ohio EPA covering wetlands and stream impacts on private land (PORTS-Pike Technology Campus)[2]
- Mar 20, 2026 DOE, SoftBank and SB Energy announce 10 GW data center campus and 9.2 GW gas generation at the Portsmouth site (PORTS-Pike Technology Campus)[3]
- Mar 2026 Groundbreaking ceremony held (PORTS-Pike Technology Campus)[2]
Notes
Planned capacity adds each record’s first published figure for projects not cancelled or denied; projects that publish none are never estimated. IT load is the power reaching computing equipment, so a total that includes it understates total power. Locations may be approximate where a record gives only a town or county. Counts cover tracked projects, not every data center.
Sources
- OpenAI, “OpenAI joins PORTS-Pike project”, Aug 17, 2026. https://openai.com/index/openai-joins-ports-pike-project/
- WOUB Public Media, “A company's plan for a massive data center complex in Pike County includes private land as well”, Jun 15, 2026. https://woub.org/2026/06/15/company-plan-massive-data-center-complex-pike-county-includes-private-land/
- U.S. Department of Energy, “FACT SHEET: The Department of Energy is Ensuring Affordable Energy Access in Ohio While Powering the Future of AI”, Mar 20, 2026. https://www.energy.gov/articles/fact-sheet-department-energy-ensuring-affordable-energy-access-ohio-while-powering-future