Data center fact sheet · county
Doña Ana County, New Mexico
As of . Latest dated change shown: Sep 24, 2026. Source: Data Center Census (datacentercensus.com), CC BY 4.0.
- Tracked projects
- 1
- 1 under construction
- Planned capacity
- 2.46 GW
- 1 project publishes a figure; 0 projects publish none
- Moratorium actions
- 0
- Upcoming hearings
- 0
Projects
| Project | Status | Planned capacity | Developer |
|---|---|---|---|
| Project Jupiter Santa Teresa | Under construction | 2.46 GW | STACK Infrastructure with BorderPlex Digital Assets |
Pauses and local rules
No moratorium action on record.
Upcoming votes and hearings
No upcoming hearing on record. Agendas change; check with the body before attending.
Latest changes
- Sep 24, 2026 Oracle sends developer Blue Owl Capital a force-majeure notice after a natural-gas pipeline meant to supply the project's power is delayed to February 2027 following New Mexico State Land Office permit denials; both companies say it does not change their commitment to the project (Project Jupiter)[1]
- Sep 17, 2026 NM Supreme Court denies petitions and lifts stay (Project Jupiter)[2]
- Sep 3, 2026 Attorney General Raúl Torrez files responses backing emergency petitions (Project Jupiter)[3]
- Aug 23, 2026 NM Supreme Court stays air-permit proceeding and well drilling (Project Jupiter)[2]
- Jul 28, 2026 Oracle says Bloom fuel cells will power campus; ~700 New Mexicans working onsite (Project Jupiter)[4]
- Apr 14, 2026 County Commission orders review of developer statements, including on closed-loop cooling and water (Project Jupiter)[5]
Notes
Planned capacity adds each record’s first published figure for projects not cancelled or denied; projects that publish none are never estimated. IT load is the power reaching computing equipment, so a total that includes it understates total power. Locations may be approximate where a record gives only a town or county. Counts cover tracked projects, not every data center.
Sources
- SiliconANGLE, “Oracle issues force majeure notice to developer of New Mexico data center over energy delays”, Sep 24, 2026. https://siliconangle.com/2026/09/24/oracle-issues-force-majeure-notice-to-developer-of-new-mexico-data-center-over-energy-delays/
- KVIA, “New Mexico Supreme Court denies petitions regarding Project Jupiter air quality permit, water use”, Sep 17, 2026. https://kvia.com/news/2026/09/17/new-mexico-supreme-court-denies-petitions-regarding-project-jupiter-air-quality-permit-water-use/
- New Mexico Department of Justice, “Attorney General Raúl Torrez Files Responses Backing Emergency Petitions Challenging Project Jupiter Permitting Decisions”, Sep 3, 2026. https://nmdoj.gov/press-release/attorney-general-raul-torrez-files-responses-backing-emergency-petitions-challenging-project-jupiter-permitting-decisions/
- Oracle, “Project Jupiter Will Bring More Than $4.7 Billion to New Mexico and Hundreds of Jobs for State Residents”, Jul 28, 2026. https://www.oracle.com/news/announcement/project-jupiter-2026-07-28/
- Doña Ana County, “County Commissioners Adopt Resolution on Project Jupiter Communications”, Apr 14, 2026. https://www.donaana.gov/news_detail_T7_R102.php
Each project record lists all of its sources and excerpts. Cite as: Data Center Census, “Data center fact sheet: Doña Ana County, New Mexico,” October 14, 2026, https://datacentercensus.com/fact-sheets/new-mexico/dona-ana-county.