Data Center Census Near me

Data center fact sheet · county

Calvert County, Maryland

As of . Latest dated change shown: Aug 4, 2026. Source: Data Center Census (datacentercensus.com), CC BY 4.0.

Full county page

Tracked projects
1
1 cancelled
Planned capacity
None published
0 projects publish a figure; 0 projects publish none; 1 cancelled or denied not counted
Moratorium actions
0
Upcoming hearings
0

Projects

ProjectStatusPlanned capacityDeveloper
Calvert Technology Center
Lusby
Cancelled500 MWAmazon Web Services (Amazon Data Services)

Pauses and local rules

No moratorium action on record.

Upcoming votes and hearings

No upcoming hearing on record. Agendas change; check with the body before attending.

Latest changes

  • Aug 4, 2026 Calvert County government issues a news release saying Amazon Web Services is abandoning its plans for data centers on the Calvert Cliffs Nuclear Power Plant campus (Calvert Technology Center)[1]
  • Jun 23, 2026 Calvert County primary election, in which voters push back against hyperscale data centers (Calvert Technology Center)[1]
  • May 2026 Amazon submits its proposal to Calvert County (Calvert Technology Center)[1]
  • Apr 2026 Amazon reveals it may develop a data center close to the Calvert Cliffs Nuclear Power Plant, according to DatacenterDynamics (Calvert Technology Center)[2]
  • Feb 2026 Residents first learn of plans for data centers on part of the Calvert Cliffs property in Lusby, according to WJLA (Calvert Technology Center)[3]

Notes

Planned capacity adds each record’s first published figure for projects not cancelled or denied; projects that publish none are never estimated. IT load is the power reaching computing equipment, so a total that includes it understates total power. Locations may be approximate where a record gives only a town or county. Counts cover tracked projects, not every data center.

Sources

  1. Maryland Matters, “Amazon abandons plans for data center campus at Calvert Cliffs”, Aug 4, 2026. https://marylandmatters.org/2026/08/04/amazon-abandons-plans-for-a-data-center-at-calvert-cliffs/
  2. DatacenterDynamics, “AWS pulls out of planned data center campus next to Maryland nuclear plant”, Aug 5, 2026. https://www.datacenterdynamics.com/en/news/aws-pulls-out-of-planned-data-center-campus-next-to-maryland-nuclear-plant/
  3. WJLA (7News), “Amazon abandons Calvert County data centers after community pushes back”, Aug 13, 2026. https://wjla.com/news/local/amazon-abandons-calvert-county-data-centers-after-community-pushes-back

Each project record lists all of its sources and excerpts. Cite as: Data Center Census, “Data center fact sheet: Calvert County, Maryland,” October 14, 2026, https://datacentercensus.com/fact-sheets/maryland/calvert-county.