In December 2024, the Data Center Census recorded 7 dated changes at 6 tracked projects across 5 states.

Final report for December 2024, published January 1, 2025. Last data change: . Page rebuilt .

← November 2024 January 2025 → All reports · Monthly RSS

Dated changes
7
Projects with a first milestone
2
Moratorium actions
0
Court cases filed
0

The month in one paragraph

In December 2024, the Data Center Census recorded 7 dated changes at 6 tracked projects across 5 states. 2 projects have their earliest dated milestone in the month. Events recorded include 1 approval, 1 construction or operations start. That is 4 fewer than the 11 changes recorded in November 2024.

Counts describe what was recorded in this tracker, from published filings, notices and reports. They are not a measure of everything that happened in the industry, and a month’s counts can rise later if sources dated in it are added.

Compared with November 2024

MeasureDecember 2024November 2024Change
Dated changes recorded711−4
Projects with a change610−4
States57−2
Projects with first milestone220
Approval events14−3
Denial events000
Cancellation events01−1
Construction or operations starts10+1
Moratorium actions000
Court cases filed000
Hearings and votes held000
Hearings and votes upcoming000

Projects with their first milestone in December 2024

ProjectFirst milestoneStatus now
Meta Hyperion
Holly Ridge, Richland Parish, LA
Dec 31, 2024Under construction
Project Sail
Newnan, Coweta County, GA
Dec 31, 2024Approved

A project appears here when its earliest dated timeline entry is in this month. It does not mean it was announced publicly that month.

Every dated change

DateWhat changedProject
Dec 31, 2024Atlas Development proposes $17B, 13-building data center campus WSB-TVProject Sail
Newnan, Coweta County, GA · Approved
Dec 27, 2024Amazon asks the Minnesota PUC to exempt its backup generators from Certificate of Need requirements (Docket PT7151/CN-24-435) CUREAmazon Becker Data Center
Becker, Sherburne County, MN · Paused
Dec 13, 2024Residents organized as the Coalition for Responsible Data Center Development sue the city Minnesota Star TribuneFarmington Technology Park
Farmington, Dakota County, MN · Approved
Dec 10, 2024Applied Digital petitions to annex the data center into the city of Ellendale North Dakota MonitorPolaris Forge 1
Ellendale, Dickey County, ND · Operating
Dec 2, 2024Council approves the development agreement with Tract, 4-1 Minnesota Star Tribune
Approval
Farmington Technology Park
Farmington, Dakota County, MN · Approved
Dec 2024Amazon Data Services, Inc. buys 589.843 acres in Jefferson Township, paying just over $102 million DatacenterDynamicsAWS Fayette County Data Center Campus
Jeffersonville, Fayette County, OH · Approved
Dec 2024Groundbreaking Meta
Construction or operations start
Meta Hyperion
Holly Ridge, Richland Parish, LA · Under construction

How this report is made

Generated from the Census records at build time. It lists dated timeline events, hearings, lawsuit filing dates and moratorium actions that fall in the month; each links to its project record and source. A month-only date belongs to its month. Entries dated only to a year are not placed in a month. Approval, denial, cancellation and construction counts are made by reading the wording of each dated event, so one event can count in more than one group, and a vote on a related item can be miscounted; open the linked record to read the source. Nothing is estimated.

The same data is behind the statistics page, the charts and the downloads.

Cite this page

Last updated Oct 14, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). U.S. data centers in December 2024. Retrieved from https://datacentercensus.com/reports/2024-12
MLA“U.S. data centers in December 2024.” Data Center Census, Oct 14, 2026, https://datacentercensus.com/reports/2024-12.
Linkhttps://datacentercensus.com/reports/2024-12

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.