Data Center Census Near me

Monthly report

U.S. data centers in September 2024

In September 2024, the Data Center Census recorded 5 dated changes at 5 tracked projects across 5 states.

Final report for September 2024, published October 1, 2024. Last data change: . Page rebuilt .

← August 2024 October 2024 → All reports · Monthly RSS

Dated changes
5
Projects with a first milestone
0
Moratorium actions
0
Court cases filed
0

The month in one paragraph

In September 2024, the Data Center Census recorded 5 dated changes at 5 tracked projects across 5 states. Events recorded include 1 approval. That is 4 fewer than the 9 changes recorded in August 2024.

Counts describe what was recorded in this tracker, from published filings, notices and reports. They are not a measure of everything that happened in the industry, and a month’s counts can rise later if sources dated in it are added.

Compared with August 2024

MeasureSeptember 2024August 2024Change
Dated changes recorded59−4
Projects with a change57−2
States56−1
Projects with first milestone03−3
Approval events13−2
Denial events000
Cancellation events000
Construction or operations starts000
Moratorium actions000
Court cases filed000
Hearings and votes held000
Hearings and votes upcoming000

Every dated change

DateWhat changedProject
Sep 24, 2024At a commissioners meeting, the county's economic development director confirms the county signed nondisclosure agreements with the prospective buyer The AssemblyMicrosoft Mega Park
Person County, NC · Proposed
Sep 17, 2024Board of Supervisors approves the rezoning 6-1 Fredericksburg Free Press
Approval
Stafford Technology Campus
Stafford County, VA · Under construction
Sep 2024Site work and building pad construction under way at the Madison County campuses Magnolia TribuneAmazon Web Services Madison County Mega Site campus
Canton, Madison County, MS · Operating
Sep 2024TPG sues Quantum Loophole; settlement in Dec. 2024 removes Quantum Loophole as manager, and TPG/Catellus take over Data Center FrontierQuantum Frederick
Adamstown, Frederick County, MD · Under construction
Sep 2024Colossus begins operations with 100,000 Nvidia H100 GPUs WikipediaxAI Colossus
Memphis, Shelby County, TN · Operating

How this report is made

Generated from the Census records at build time. It lists dated timeline events, hearings, lawsuit filing dates and moratorium actions that fall in the month; each links to its project record and source. A month-only date belongs to its month. Entries dated only to a year are not placed in a month. Approval, denial, cancellation and construction counts are made by reading the wording of each dated event, so one event can count in more than one group, and a vote on a related item can be miscounted; open the linked record to read the source. Nothing is estimated.

The same data is behind the statistics page, the charts and the downloads.

Cite this page

Last updated Oct 14, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). U.S. data centers in September 2024. Retrieved from https://datacentercensus.com/reports/2024-09
MLA“U.S. data centers in September 2024.” Data Center Census, Oct 14, 2026, https://datacentercensus.com/reports/2024-09.
Linkhttps://datacentercensus.com/reports/2024-09

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.