Monthly report
U.S. data centers in November 2022
In November 2022, the Data Center Census recorded 2 dated changes at 2 tracked projects across 2 states.
Final report for November 2022, published December 1, 2022. Last data change: . Page rebuilt .
← September 2022 February 2023 → All reports · Monthly RSS
- Dated changes
- 2
- Projects with a first milestone
- 0
- Moratorium actions
- 0
- Court cases filed
- 0
The month in one paragraph
In November 2022, the Data Center Census recorded 2 dated changes at 2 tracked projects across 2 states. That is 2 more than the 0 changes recorded in October 2022.
Counts describe what was recorded in this tracker, from published filings, notices and reports. They are not a measure of everything that happened in the industry, and a month’s counts can rise later if sources dated in it are added.
Compared with October 2022
| Measure | November 2022 | October 2022 | Change |
|---|---|---|---|
| Dated changes recorded | 2 | 0 | +2 |
| Projects with a change | 2 | 0 | +2 |
| States | 2 | 0 | +2 |
| Projects with first milestone | 0 | 0 | 0 |
| Approval events | 0 | 0 | 0 |
| Denial events | 0 | 0 | 0 |
| Cancellation events | 0 | 0 | 0 |
| Construction or operations starts | 0 | 0 | 0 |
| Moratorium actions | 0 | 0 | 0 |
| Court cases filed | 0 | 0 | 0 |
| Hearings and votes held | 0 | 0 | 0 |
| Hearings and votes upcoming | 0 | 0 | 0 |
Every dated change
| Date | What changed | Project |
|---|---|---|
| Nov 15, 2022 | Village Board takes up a resolution recommending future renewal of the Class 6B classification for the Mount Prospect Technology Campus Village of Mount Prospect, IL | CloudHQ ORD Campus Mount Prospect, Cook County, IL · Under construction |
| Nov 1, 2022 | Board of County Supervisors adopts the comprehensive plan amendment for the Digital Gateway area Potomac Local | Prince William Digital Gateway Gainesville, Prince William County, VA · Cancelled |
How this report is made
Generated from the Census records at build time. It lists dated timeline events, hearings, lawsuit filing dates and moratorium actions that fall in the month; each links to its project record and source. A month-only date belongs to its month. Entries dated only to a year are not placed in a month. Approval, denial, cancellation and construction counts are made by reading the wording of each dated event, so one event can count in more than one group, and a vote on a related item can be miscounted; open the linked record to read the source. Nothing is estimated.
The same data is behind the statistics page, the charts and the downloads.
Cite this page
Last updated Oct 14, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). U.S. data centers in November 2022. Retrieved from https://datacentercensus.com/reports/2022-11 |
|---|---|
| MLA | “U.S. data centers in November 2022.” Data Center Census, Oct 14, 2026, https://datacentercensus.com/reports/2022-11. |
| Link | https://datacentercensus.com/reports/2022-11 |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.