Monthly report
U.S. data centers in July 2019
In July 2019, the Data Center Census recorded 2 dated changes at 1 tracked project across 1 state.
Final report for July 2019, published August 1, 2019. Last data change: . Page rebuilt .
← March 2019 March 2021 → All reports · Monthly RSS
- Dated changes
- 2
- Projects with a first milestone
- 0
- Moratorium actions
- 0
- Court cases filed
- 0
The month in one paragraph
In July 2019, the Data Center Census recorded 2 dated changes at 1 tracked project across 1 state. Events recorded include 1 approval. That is 2 more than the 0 changes recorded in June 2019.
Counts describe what was recorded in this tracker, from published filings, notices and reports. They are not a measure of everything that happened in the industry, and a month’s counts can rise later if sources dated in it are added.
Compared with June 2019
| Measure | July 2019 | June 2019 | Change |
|---|---|---|---|
| Dated changes recorded | 2 | 0 | +2 |
| Projects with a change | 1 | 0 | +1 |
| States | 1 | 0 | +1 |
| Projects with first milestone | 0 | 0 | 0 |
| Approval events | 1 | 0 | +1 |
| Denial events | 0 | 0 | 0 |
| Cancellation events | 0 | 0 | 0 |
| Construction or operations starts | 0 | 0 | 0 |
| Moratorium actions | 0 | 0 | 0 |
| Court cases filed | 0 | 0 | 0 |
| Hearings and votes held | 0 | 0 | 0 |
| Hearings and votes upcoming | 0 | 0 | 0 |
Every dated change
| Date | What changed | Project |
|---|---|---|
| Jul 9, 2019 | Compass announces that construction has started on the campus's first two data centers Compass Datacenters | Compass Datacenters Goodyear Campus Goodyear, Maricopa County, AZ · Under construction |
| Jul 8, 2019 | Goodyear City Council unanimously approves an agreement for the 225-acre Compass campus Greater Phoenix Economic Council (GPEC) Approval | Compass Datacenters Goodyear Campus Goodyear, Maricopa County, AZ · Under construction |
How this report is made
Generated from the Census records at build time. It lists dated timeline events, hearings, lawsuit filing dates and moratorium actions that fall in the month; each links to its project record and source. A month-only date belongs to its month. Entries dated only to a year are not placed in a month. Approval, denial, cancellation and construction counts are made by reading the wording of each dated event, so one event can count in more than one group, and a vote on a related item can be miscounted; open the linked record to read the source. Nothing is estimated.
The same data is behind the statistics page, the charts and the downloads.
Cite this page
Last updated Oct 14, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). U.S. data centers in July 2019. Retrieved from https://datacentercensus.com/reports/2019-07 |
|---|---|
| MLA | “U.S. data centers in July 2019.” Data Center Census, Oct 14, 2026, https://datacentercensus.com/reports/2019-07. |
| Link | https://datacentercensus.com/reports/2019-07 |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.