In August 2023, the Data Center Census recorded 3 dated changes at 3 tracked projects across 3 states.
Final report for August 2023, published September 1, 2023. Last data change: . Page rebuilt .
← June 2023 September 2023 → All reports · Monthly RSS
- Dated changes
- 3
- Projects with a first milestone
- 3
- Moratorium actions
- 0
- Court cases filed
- 0
The month in one paragraph
In August 2023, the Data Center Census recorded 3 dated changes at 3 tracked projects across 3 states. 3 projects have their earliest dated milestone in the month. That is 3 more than the 0 changes recorded in July 2023.
Counts describe what was recorded in this tracker, from published filings, notices and reports. They are not a measure of everything that happened in the industry, and a month’s counts can rise later if sources dated in it are added.
Compared with July 2023
| Measure | August 2023 | July 2023 | Change |
|---|---|---|---|
| Dated changes recorded | 3 | 0 | +3 |
| Projects with a change | 3 | 0 | +3 |
| States | 3 | 0 | +3 |
| Projects with first milestone | 3 | 0 | +3 |
| Approval events | 0 | 0 | 0 |
| Denial events | 0 | 0 | 0 |
| Cancellation events | 0 | 0 | 0 |
| Construction or operations starts | 0 | 0 | 0 |
| Moratorium actions | 0 | 0 | 0 |
| Court cases filed | 0 | 0 | 0 |
| Hearings and votes held | 0 | 0 | 0 |
| Hearings and votes upcoming | 0 | 0 | 0 |
Projects with their first milestone in August 2023
| Project | First milestone | Status now |
|---|---|---|
| Brightseat Tech Park Landover, Prince George's County, MD | Aug 16, 2023 | Approved |
| Amazon Web Services Louisa County campuses Louisa, Louisa County, VA | Aug 31, 2023 | Under construction |
| Project Borealis Mesa, Maricopa County, AZ | Aug 31, 2023 | Approved |
A project appears here when its earliest dated timeline entry is in this month. It does not mean it was announced publicly that month.
Every dated change
| Date | What changed | Project |
|---|---|---|
| Aug 16, 2023 | Reports say Lerner has filed a natural resources inventory for the former Landover Mall site, a first step toward a data center, while the site competes for the FBI headquarters NBC4 Washington | Brightseat Tech Park Landover, Prince George's County, MD · Approved |
| Aug 2023 | AWS announces plan for two campuses in Louisa County, $11 billion by 2040 DatacenterDynamics | Amazon Web Services Louisa County campuses Louisa, Louisa County, VA · Under construction |
| Aug 2023 | Novva wins a state land auction for about 165 acres in southeast Mesa with a $62.7 million bid ABC15 / Phoenix Business Journal | Project Borealis Mesa, Maricopa County, AZ · Approved |
How this report is made
Generated from the Census records at build time. It lists dated timeline events, hearings, lawsuit filing dates and moratorium actions that fall in the month; each links to its project record and source. A month-only date belongs to its month. Entries dated only to a year are not placed in a month. Approval, denial, cancellation and construction counts are made by reading the wording of each dated event, so one event can count in more than one group, and a vote on a related item can be miscounted; open the linked record to read the source. Nothing is estimated.
The same data is behind the statistics page, the charts and the downloads.
Cite this page
Last updated Oct 14, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). U.S. data centers in August 2023. Retrieved from https://datacentercensus.com/reports/2023-08 |
|---|---|
| MLA | “U.S. data centers in August 2023.” Data Center Census, Oct 14, 2026, https://datacentercensus.com/reports/2023-08. |
| Link | https://datacentercensus.com/reports/2023-08 |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.